Teddington's launch lock will not reopen until early 2027, the Environment Agency says. The refurbished gates are now back in and testing starts soon.

The launch lock at Teddington will not reopen to boats until early 2027. That is the third date the Environment Agency has given for the job, which started in September 2025.

The agency said in its November update, published by Richmond Council on 12 November, that both sets of refurbished gates are now back in place. It called that “a key milestone”. Work on site will carry on through the winter.

The launch lock is one of three locks side by side at Teddington. The barge lock has stayed open throughout the work, so the river is not closed to navigation.

How the date has moved

Update Expected reopening
28 November 2025 Summer 2026
20 July 2026 Autumn 2026
12 November 2026 Early 2027

In July the agency said it had been working to reopen the lock by the end of the boating season, but that this was “now unlikely to be achieved”.

Why it has taken longer

The lock is more than 100 years old. The agency says its true condition could only be assessed once the chamber was drained and surveyed, and the surveys showed the structure differed from the historical records. That meant the design had to be adjusted as construction went on.

Much of the work has had to be precise to within plus or minus 1mm. The agency also blames the prolonged hot, dry summer, which affected the concrete work.

What has been done

According to the Environment Agency’s project update, its contractor BAM has:

  • reinforced and rebuilt key sections of the chamber walls
  • removed damaged parts and built new ones to modern standards
  • fitted the hydraulic lines, cables and pedestals the lock keeper will use to work the gates
  • installed both refurbished sets of gates, at the head and the tail of the lock
Aerial view of the drained Teddington launch lock chamber with workers in orange, a crane and plant on the lock sides, and boats moored in the river beside it
The launch lock chamber during the works. Photo: Environment Agency

Testing comes next

The gates will now be tested both wet and dry, which means filling and draining the chamber several times. The new mechanical and electrical equipment will be tested too.

The agency says the testing is being planned around the Port of London Authority’s annual drawdown, which began on 5 November.

What it means for you

  • If you have a small boat: keep using the barge lock. The launch lock stays shut until early 2027 at the earliest.
  • If you walk the towpath: the weekday towpath closures at the lock run until about March.
  • If you have a question about the works: the project team is on enquiries_thm@environment-agency.gov.uk.

Updates appear on the agency’s Thames Area Assets page.